Nord Stream 2 has reported that about 121 kilometres of pipe are left to be laid
According to TASS, Nord Stream 2 AG, the operator of the project, told journalists that Nord Stream 2 is currently 95% ready.
“As of March 31, 2,339 km (out of 2,460 km) or 95% of the Nord Stream 2 pipeline has been laid. About 121 km (5%) of the total pipeline length remains to be laid”, – the company said.