Work will continue until the end of the third quarter of the year.
According to TASS, the schedule of Nord Stream 2 AG, which was provided to TASS by the Danish Energy Agency (DEA), indicated that work on laying the second string of the Nord Stream-2 gas pipeline in the exclusive economic zone of Denmark should begin at the end of this month.
“Scheme of construction of line A. The preparatory stage is scheduled for mid-March. It is envisaged that pipe-laying will resume at the end of March and will continue until the end of the third quarter”, – the document says.
As explained earlier in DEA, before the start of work, Nord Stream-2 AG must submit an adjusted schedule. The agency does not need to approve it.